What amount should be added to net capital assets in the governmental activities accounts in 2012?
In 2011, Weaver City signed a contract in the amount of $6,000,000 for the construction of a new city hall. Expenditures were $4,000,000 in 2011 and $2,050,000 in 2012, which included a change to the original construction design in the amount of $50,000. What amount should be added to net capital assets in the governmental activities accounts in 2012? (Points : 2)
$6,000,000
$6,050,000
$2,050,000
$2,000,000.